Charles Street Reconstruction Project
Balto City Seal
Page Updated on:
March 23, 2004
Schedule

CHARLES STREET RECONSTRUCTION STAKEHOLDER COMMITTEE

60-DAY RESOLUTION SCHEDULE

... a transparent and aggressive schedule leading to a revised consensus plan for the reconstruction of Charles Street from 25th Street to University Parkway by early January 2003.

November 2002

December 2002

January 2003

Preliminary Design Schedule

  1. Preliminary Design (30% complete)
    Begin
    Stakeholder's Review Meeting
    Complete Preliminary Design
    January 2003
    March 2003
    April 2003

  2. Semi-Final Design (60% complete)
    Begin
    Stakeholder's Review Meeting
    Complete Semi-Final Design
    May 2003
    August 2003
    November 2003

  3. Final Design (95% complete)
    Begin
    Stakeholder's Review Meeting
    Complete Final Design
    December 2003
    February & March 2004
    May 2004

  4. City / SHA Approval
    September 2004

  5. Advertisement / Bid Phase
    Begin
    Complete Bid Phase
    October 2004
    February 2005

  6. Construction
    Begin
    Complete Construction / Ribbon Cutting
    May 2005
    November 2006